In the DMAIC framework, which phase follows Measure?

Master Comprehensive Business Management with our targeted quiz. Reinforce your decision-making skills through interactive flashcards and multiple choice questions. Prepare effectively for your test today!

Multiple Choice

In the DMAIC framework, which phase follows Measure?

Explanation:
The phase that follows Measure is Analyze. After you’ve collected reliable data and established a baseline in Measure, Analyze uses that data to uncover the root causes of defects and variation. It’s about turning measurements into understanding—testing hypotheses, identifying which factors most affect performance, and determining where the process is failing to meet goals. This sets up the next steps, where you design and implement improvements to address those root causes, and then put controls in place to sustain the gains.

The phase that follows Measure is Analyze. After you’ve collected reliable data and established a baseline in Measure, Analyze uses that data to uncover the root causes of defects and variation. It’s about turning measurements into understanding—testing hypotheses, identifying which factors most affect performance, and determining where the process is failing to meet goals. This sets up the next steps, where you design and implement improvements to address those root causes, and then put controls in place to sustain the gains.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy